Projects
Roadmap
From Novel IP to Full-Scale Process Plant

1. Novel IP Development
🧪
-
Activities: Lab-scale experiments, IP engineering, initial FTO (freedom to operate) analysis
-
Expected Output: Proprietary Nitric Acid Leach (NAL) formulation with initial AI/IoT integration
-
Milestone: Internal validation and IP documentation
Intellectual Property Secured
➡️ Next: Validate commercially viable economics
2. Advanced Feasibility Study (AFS) + Metallurgical Testing
📊
-
Activities: Bulk ore sampling, metallurgical bench-scale tests, CAPEX/OPEX modeling, ESG & impact analysis, advance AI/IoT design & 1–3 TPD modular pilot
-
Output: Full Techno-Economic Analysis (TEA), environmental permitting pathway, Process Plant Engineering Design, Initial Carbon Credit Frameworks
-
Milestone: Investor-grade report aligned with JORC/PMRC/NI43-101 standards
📘 Decision Point: Greenlight Pilot Plant
➡️ Next: Prove technical scalability and off-taker interest
3. Revenue Generating Pilot Plant Deployment
🏗️
-
Activities: 300,000 DMT/year modular plant (Phase 1), real ore throughput, energy efficiency metrics, AI automation tuning, Carbon Credit Frameworks + application
-
Output: Confirmed recovery rates for Ni, Co, Sc, REEs; produce sample material for offtakers
-
Milestone: Strategic Offtake LOIs, government permits in motion
🔁 Iterate IP + File Enhanced Patents (if needed)
➡️ Next: Scale to commercial capacity
4. Full-Scale Commercial Plant
🏭
-
Activities: Up to 1.5M DMT/year (Phase 2)
-
Output: >$1B - $2.5 in Revenue potential, global offtake, ESG-certified operation, Carbon Credits
-
MVP : Premium Ingots of Gold, Copper, Nickel, Cobalt, Scandium and Laterite by-products (HPA, Mg to Agri-chemicals)
-
Milestone: First shipment of refined nickel and co-products, strategic expansion readiness
🌐 Market Positioning: Philippines as Processing Hub